(1) Faults caused by component materials in the Ready Boards with Bulkhead Light:

 

① There is a big gap between the manual of Ready Boards with Bulkhead Light and the real technical data.

 

② The purchase and storage management of Ready Boards with Bulkhead Lights is not strict.

 

③ The technical disclosure for the construction of Ready Boards with Bulkhead Light is not clear, which brings unnecessary constraints to the installation and use of Ready Boards with Bulkhead Light, resulting in operation failure.

 

(2) Ready Boards with Bulkhead Light failure caused by construction:

 

① The quality control of the accessory materials of the Ready Boards with Bulkhead Light is not strict, causing hidden dangers to the safe operation.

 

② The installation process is not up to standard, for example, the box body is not thoroughly cleaned.

 

③ The material configuration of accessories in the Ready Boards with Bulkhead Light is not up to standard.

 

④ Insufficient and unobtrusive signs in the Ready Boards with Bulkhead Light and inadequate sealing treatment of the Ready Boards with Bulkhead Light in a humid environment have left hidden dangers for the operation of the Ready Boards with Bulkhead Light.

 

(3) Ready Boards with Bulkhead Light failure caused by poor management and maintenance of the operating unit:

 

① The maintenance inspection test cannot be carried out regularly.

 

② Faults caused by seasonal natural rain, wind and snow, scorching sun and other factors, such as; Corrosion and looseness of grounding bolts.

 

(4) Ready Boards with Bulkhead Light failure caused by other reasons:

 

① The long-term calculation cannot be considered for the temporary charge load, or the statistics are not thorough, so the Ready Boards with Bulkhead Light runs overloaded and causes faults.

 

② The wiring holes at the upper and lower ends of components in the Ready Boards with Bulkhead Light do not match the diameter and section of incoming and outgoing lines or cables, resulting in potential power supply hazards.

 

③ When other disciplines construct near the Ready Boards with Bulkhead Light, the power supply circuit is damaged, resulting in short circuit or grounding, resulting in Ready Boards with Bulkhead Light failure.